Forthcoming Roadworks in the Ealing Area
Closures and diversions which may cause problems
 Weekend Traffic Likely in Ealing Due To A4 Closures
Great West Road shut to enable work on elevated section of M4
Nine Month Delay to Gunnersbury Avenue Roadworks
Power Road bridge project lane closures to continue until autumn 2018
A406,A4005 Hanger Lane, Ealing |
31 October — 01 November |
Delays likely Traffic control (two-way signals) |
Works description: techjoint manhole replacement |
Responsibility for works: Transport for London |
Current status: Planned work about to start |
Works reference: YG430334588 |
|
A4020 New Broadway, Ealing |
28 October — 04 November |
Delays likely Traffic control (two-way signals) |
Works description: Install 10m of 1 way poly duct in Carriageway,Install 2m of 1 way poly duct in Footway |
Responsibility for works: Openreach |
Current status: Planned work about to start |
Works reference: BC006TI001LC500258806503 |
|
B455 Castlebar Road, Ealing |
30 October — 02 November |
Delays likely Traffic control (two-way signals) |
Works description: 3x25mm MDPE new water meetr supply in f.way and in Carriageway. Ourintention is to complete the Permanent Reinstatement in the same phase |
Responsibility for works: THAMES WATER |
Current status: Planned work about to start |
Works reference: MU307000804381320265-002 |
|
Longfield Avenue, Ealing |
28 October — 04 November |
Delays likely Road closure |
Works description: Install 2m of 1 way poly duct in Carriageway |
Responsibility for works: Openreach |
Current status: Planned work about to start |
Works reference: BC006TI001LC500258806502 |
|
November 1, 2018
|